flex7 Applications – Absence Control With Daylight Linking To Window Luminaires

Wiring Connection

DESCRIPTION | PART NO. |
---|---|
1 X Starter Distribution Box | FSU08 |
1 x Control Pack | FNC4000X/AB |
1 x Switch | FWS01/K/AB/W/WP |
1 x Primary PIR Sensor Head | FNH400 |
1 x Switch Drop Lead | FSL10/BL |
1 x Sensor Lead | FSL05 |
3 X Standard (on/off) Luminaire Lead | FL3100LSHF5/W |
1 X Maintained Emergency Luminaire Lead | FL4100LSHF5/R |
1 X DALI Luminaire Lead | FL5100LSHF5/BD |
1 X DALI Maintained Emergency Luminaire Lead | FL6100LSHF5/RD |
1 X Setup Remote Control | FRC/SET |
Control Device Properties
Switch is a 2-position retractive type ie. it can be pulsed up/down but when released always returns to the centre position.
Sensor Head is a passive infrared (PIR) device that detects movement within a defined area – 9m x 7m each when mounted at a height of 2.5m.
PIR Sensor Head also includes an integral light sensor that can measure variations in the available ambient light.
Switch and PIR Sensor Head both operate at Protected Extra Low Voltage (PELV) – nominally 5V and 12V respectively.
Operation
Luminaires are all turned on manually using the flex7 Switch. Pulse in one direction to send an on signal.
The integral light sensor measures the available ambient light and maintains the area’s set target level by decreasing or increasing the light output of the luminaires adjacent to the window.
Once the area is vacated and the PIR Sensor Head has completed its timeout sequence the luminaires will automatically switch off.
Alternatively, pulsing the switch to send an off signal will turn all the luminaires off before the timeout sequence has elapsed.
Luminaires adjacent to the window must have DALI drivers /control gear.
Installation
- Install the Distribution Box using the fixing kit provided.
- Terminate the fixed wiring into the Distribution Box terminals – see schematic above.
- Fit the Switch – it mounts onto a standard 25mm deep single box with 60.3mm centres.
- Fit the PIR Sensor Head – it requires a 32mm hole.
- Plug the Control Pack into any outlet on the Distribution Box.
- Plug one end of the Switch Drop Lead into the Control Pack.
- Plug one end of the Switch Drop Lead into the Switch.
- Plug one end of the Sensor Lead into the Control Pack.
- Plug one end of the Sensor Lead into a PIR Sensor Head.
- Plug the luminaires into any outlet on the Distribution Box.
- Using a Setup Remote Control (FRC/SET) set the desired target light level.
Tips and Tricks
One of our Setup Remote Control (FRC/SET) is required to set the desired target light level – instructions are provided.
To stop daylight linking being interfered with from the switch, the FRC/SET can be used to disable manual dimming.